Bonded straight to the subfloor

BON flooring has its own dense, impervious backing, so it is glued down with no underlay. The subfloor must be level, dry, sound and clean.

Section through an installed tile

  1. 1Nylon 6.6 flock
  2. 2Acrylic resin and stabilising layers
  3. 3Virgin PVC backingBON tile ends here
  4. 4Adhesivebought and applied locally
  5. 5Subfloorlevel, dry, sound, clean

Section, not to scale. Layers from BON’s tile construction drawing.

Subfloor requirements

Exact tolerances are set by local practice and your adhesive supplier, and differ by market. The conditions below apply everywhere.

When an extra layer is needed

Most floors need no underlay. In the situations below, the contractor or consultant may specify an extra layer for the building.

  1. 1A subfloor too uneven to skim. The substrate has to be put right first, because a thin, dense covering shows what is underneath.
  2. 2Residual moisture above the adhesive’s limit. Specify a surface damp-proof membrane rather than waiting for the reading to fall.
  3. 3Refurbishment over an existing floor. Where the old floor cannot come up, an isolating layer may be specified.
  4. 4An acoustic target above the covering’s own. ΔLw 21 dB (ISO 10140-1 / 717-2, SGS) is the contribution of the floor covering alone. A higher target has to be met by the whole floor build-up.

Adhesive

We do not ship adhesive.

Use a pressure-sensitive or permanent-set flooring adhesive suited to an impervious-backed textile covering, chosen with your local supplier for the subfloor, moisture level and traffic. Trowel notch, open time and coverage depend on conditions in the building, so a product made for your climate works better than one shipped from China.

Laying patterns

Tiles are laid quarter-turn, monolithic, brick offset or in mixed colourways. Planks of 25 × 100 cm are laid herringbone or with a random offset.

1763·060 and 1763·230, 50 cm tiles laid quarter-turn.
1763·060 and 1763·230, 50 cm tiles laid quarter-turn.
1760·060 and 1760·241, laid in one direction.
1760·060 and 1760·241, laid in one direction.
1755·041 and 1755·042, 25 × 100 cm planks laid herringbone.
1755·041 and 1755·042, 25 × 100 cm planks laid herringbone.
1757·012 planks with a random offset.
1757·012 planks with a random offset.
1620060Dot

Laid quarter-turn · 16 tiles of 50 × 50 cm · 2.0 × 2.0 m

Try the laying patterns

Pick a series and switch between the patterns it can be laid in. Tiles are shown 4 × 4, planks over the same 2 × 2 m.

Laying steps

Tiles and planks are laid in the same order of work. Rolls also have seams to cut and roll.

Tiles and planks

  1. Acclimatise

    Store the cartons flat and unopened in the room to be laid, at the temperature it will be used at, before laying.

  2. Set out

    Find the centre of the room and mark two lines at right angles. Lay from the centre outwards so the cut pieces at the walls come out even.

  3. Choose the direction

    Keep every tile the same way round for monolithic, or turn alternate tiles 90° for quarter-turn. Planks are laid with a random offset or herringbone.

  4. Lay and press

    Lay each piece tight against its neighbours into the adhesive, without trapping pile in the joints, and roll each section once it is down.

  5. Cut in

    Cut the perimeter pieces from the back with a sharp knife against a straightedge.

Roll

  1. Relax the roll

    Unroll the cut lengths in the room and let them lie flat before fixing.

  2. Plan the seams

    Run all lengths the same way, and keep seams out of doorways and the heaviest traffic where possible.

  3. Double-cut

    Overlap the second length on the first and cut through both together, so the seam closes tight.

  4. Fix

    Fold back half a length, spread the adhesive, lay it back and roll from the centre to the edges. Repeat for the other half.

  5. Roll the seams

    Roll the seams again once both lengths are down, and keep traffic off until the adhesive has set.

Stairs

Tiles and roll can both be laid on stairs, with a stair-nosing profile fitted to the edge of each tread. Fix the covering to tread and riser separately and finish it against the nosing.

Scope of supply

Supplied by BON

The floor covering in the specified format, series and colourway; the dated test report for your product and batch; packing and export documents.

Handled locally, outside an FOB price

Subfloor survey, levelling compound, moisture testing, any damp-proof membrane, adhesive, installation labour, waste removal, and site temperature and humidity.

After installation

Let the adhesive cure before the floor is used, then bring it into service in this order.

  1. 1Foot trafficonce the adhesive has cured
  2. 2Furniture
  3. 3Rolling loads
  4. 4Wet cleaninglast

For daily care, vacuum and spot-clean. Periodically wet-mop, extraction-clean or steam-clean. The backing is impervious, so water lifts soil off the surface and does not soak in.

Cleaning and maintenance

Your sample set

Add tiles from any series, then send the set with your enquiry. Colours on screen are indicative. Judge the colour from the tiles we send you.

No tiles yet. Add any colourway from a series page.

Request samples
Email
manager@bohuazr.com
WhatsApp
+86 138 6735 8518
Telephone
+86 573 8491 5268
Factory
No. 35 Ninghong Road, Tianning Town, Jiashan, Zhejiang, China